Japan

JAPAN

First Nuclear Power Plant Opened: Operations at the first nuclear power reactor began in July, 1966. Tokai-1, the first commercial reactor, was a 160 MW gas-cooled reactor built by GEC and was imported from the United Kingdom. Japan's nuclear research program began in 1954.
Number and Types of Nuclear Power Plants: 54 reactors are currently in operation (listed below).
Percentage of National Energy From Nuclear Power: 34% (plans are underway to increase the percentage of national energy from nuclear power to 42% by 2010). Japan has the third largest installed nuclear capacity, behind only the US and France.
Future Nuclear Power Plans: Japan currently has three reactors under construction with eleven planned or on order (listed below).

ANALYSIS / ISSUES

As an island-nation, Japan cannot trade energy with its neighbors via power transmission lines, which poses a problem for inexpensive energy exchanges. Natural resources pose a second problem for Japan as it has very few natural energy options and must depend on energy-imports for 80% of its energy resources. Utilizing nuclear energy to the fullest extent is just one way in which Japan's energy program is working to overcome its natural difficulties. The energy program also depends upon both thermal and hydroelectric power. The creation of an extensive nuclear power program is an attempt to diversify Japanese energy alternatives in order to prevent heavy reliance on any one source. By not diversifying, Japan could run the risk of potentially jeopardizing Japan's energy security. As a heavy importer, the country was struck by two oil crises (one being the 1973 Arab oil embargo) and has since made an effort to expand its approach to energy programming. Nuclear energy is an attractive option that continues to increase in importance, as it is a stable power source that can help to relieve environmental problems.

Public opposition to the nuclear power program in Japan has increased in recent years as a result of a string of nuclear power plant accidents in that country. One of these incidents included a fire and explosion at the Tokai-mura reprocessing plant in March 1997. The Janurary 17, 1995 Kobe earthquake raised concerns about the safety of nuclear power plant facilities and the threat of earthquakes. While Kobe and the surrounding area sustained much damage, none of the power plants within a 200km radius were affected, and they all continued to run at normal capacity. Although nuclear power plants are designed to withstand natural disasters such as earthquakes, there is concern as to the frequency and high magnitude of Japanese earthquakes. This concern has led to an increased level of attention paid to the safe design of Japanese power plants.

The Japanese government has made a point of advocating the recovery of uranium and plutonium through the reprocessing of spent fuel. This process adds security to Japan's nuclear energy program. In 2003, Japan's stockpile of plutonium surpassed the amount of plutonium found in the US nuclear arsenal. At that time Japan owned 38 tons of plutonium, with 33 of those tons located at Japanese-owned processors in Europe, while the remaining 5 tons stored at home. Plutonium production in Japan is not slowing down. The government of Japan explains its increased production of plutonium as an attempt to reduce its reliance on foreign uranium. Japan's store of plutonium could reach 100 tons by 2015 once a planned reprocessing plant opens in Rokkasho-mura. The Japanese Atomic Energy Commission releases an annual inventory of all of Japan's separated plutonium and the Government denies all claims that Japan hopes to institute a nuclear weapons program.

On February 28, 2005, Japan was among 11 countries to sign into effect the Generation IV International Forum (GIF), a multilateral agreement to promote the development of next generation nuclear energy systems. The participating countries now have more freedom to globally conduct joint research projects. So far, six technologies have been targeted for research: the Gas Cooled Reactor, the Sodium Fast Reactor, the Lead-Cooled Fast Reactor, the Molten Salt Reactor, the Supercritical Water Reactor, and the Very High Temperature Reactor.

In July 2005, France was named as the country to host the International Thermonuclear Experimental Reactor (ITER). Japan had also placed a bid for this reactor, but despite losing the bid to France, the EU has considered making Japan a "joint host" in the project. This title would allow Japan's Rokkasho-mura to become one of the project's research hubs while the reactor is built in France. The EU has already granted Japan $533 million worth of contracts to build related ITER facilities and an analysis center for ITER. If a second ITER is to be built in the future, the EU has pre-selected Japan as the site.


Power Reactors Operating in Japan

REACTOR TYPE NET CAPACITY (MWe) UTILITY COMMERCIAL OPERATION
Fukushima I-1 BWR 439 TEPCO March 1971
Fukushima I-2 BWR 760 TEPCO July 1974
Fukushima I-3 BWR 760 TEPCO March 1976
Fukushima I-4 BWR 760 TEPCO October 1978
Fukushima I-5 BWR 760 TEPCO April 1978
Fukushima I-6 BWR 1067 TEPCO October 1979
Fukushima II-1 BWR 1067 TEPCO April 1982
Fukushima II-2 BWR 1067 TEPCO February 1984
Fukushima II-3 BWR 1067 TEPCO June 1985
Fukushima II-4 BWR 1067 TEPCO August 1987
Genkai-1 PWR 529 Kyushu October 1975
Genkai-2 PWR 529 Kyushu March 1981
Genkai-3 PWR 1127 Kyushu March 1994
Genkai-4 PWR 1127 Kyushu July 1997
Hamaoka-1 BWR 515 Chubu March 1976
Hamaoka-2 BWR 806 Chubu November 1978
Hamaoka-3 BWR 1056 Chubu August 1987
Hamaoka-4 BWR 1092 Chubu September 1993
Hamaoka-5 ABWR 1380 Chubu January 2005
Higashidori-1 BWR 1067 Tohoku March 2005
Ikata-1 PWR 538 Shikoku September 1977
Ikata-2 PWR 538 Shikoku March 1982
Ikata-3 PWR 846 Shikoku December 1994
Kashiwazaki-Kariwa-1 BWR 1067 TEPCO September 1985
Kashiwazaki-Kariwa-2 BWR 1067 TEPCO September 1990
Kashiwazaki-Kariwa-3 BWR 1067 TEPCO August 1993
Kashiwazaki-Kariwa-4 BWR 1067 TEPCO August 1994
Kashiwazaki-Kariwa-5 BWR 1067 TEPCO April 1990
Kashiwazaki-Kariwa-6 ABWR 1315 TEPCO November 1996
Kashiwazaki-Kariwa-7 ABWR 1315 TEPCO July 1997
Mihama-1 PWR 320 Kansai November 1970
Mihama-2 PWR 470 Kansai July 1972
Mihama-3 PWR 780 Kansai December 1976
Ohi-1 PWR 1120 Kansai March 1979
Ohi-2 PWR 1120 Kansai December 1979
Ohi-3 PWR 1127 Kansai December 1991
Ohi-4 PWR 1127 Kansai February 1993
Onagawa-1 BWR 498 Tohoku June 1984
Onagawa-2 BWR 796 Tohoku July 1995
Onagawa-3 BWR 798 Tohoku January 2002
Sendai-1 PWR 846 Kyushu July 1984
Sendai-2 PWR 846 Kyushu November 1985
Shika-1 BWR 505 Hokuriku July 1993
Shimane-1 BWR 439 Chugoku March 1974
Shimane-2 BWR 789 Chugoku February 1989
Takahama-1 PWR 780 Kansai November 1974
Takahama-2 PWR 780 Kansai November 1975
Takahama-3 PWR 830 Kansai January 1985
Takahama-4 PWR 830 Kansai June 1985
Tokai-2 BWR 1056 JAPC November 1978
Tomari-1 PWR 550 Hokkaido June 1989
Tomari-2 PWR 550 Hokkaido April 1991
Tsuruga-1 BWR 341 JAPC March 1970
Tsuruga-2 PWR 1115 JAPC February 1987
Total : 54 reactors 46,342

 


Japanese Reactors Under Construction

REACTOR TYPE NET CAPACITY (MWe) UTILITY CONSTRUCTION START OPERATION
           
Shika-2 ABWR 1358 Hokuriku August 2001 2006
Tomari-3 PWR 866 Hokkaido 2003 2009
Shimane-3 ABWR 1375 Chogoku September 2005 2011
Total : 3 3599